House 5632

2026 Regular Session

Link to Bill History on Legacy Website (Click Here)

Summary: Relating to local permitting deadlines
PDF: hb5632 intr.pdf
DOCX: HB5632 INTR.docx


WEST VIRGINIA LEGISLATURE

2026 REGULAR SESSION

Introduced

House Bill 5632

By Delegates Flanigan, Pritt, Mallow, Shamblin, Stephens, G. Ward, Marple, and Holstein

[Introduced February 16, 2026; referred to the Committee on Government Organization]

A BILL to amend and reenact §8A-13-1, §8A-13-2, and §8A-13-3 of the code of West Virginia, 1931, as amended, relating to local permitting deadlines; expanding the deadlines to ensure the petitioners have adequate time for review and approval by local administrators; and eliminating conflicts with other legal notice requirements for the type of approvals required under chapter 8A.

Be it enacted by the Legislature of West Virginia:

 

ARTICLE 13. LOCAL PERMITTING DEADLINES.

 

§8A-13-1. Definition.

For purposes of this article, "request" means an application for a permit, license, variance, or any other type of prior approval from a governing body or planning commission of a municipality or county for an action related to the development or improvement of property authorized under §8A-1-1 et seq. of this code.

§8A-13-2. Deadline.

(a) If an applicant submits a request to a governing body or planning commission of a municipality or county, then the governing body or planning commission of the municipality or county must approve or deny the applicant's request within 60 days. The following applies if:

(1) The governing body or planning commission fails to approve or deny the applicant's request within 60 days, then the request is approved: Provided, That nothing in this article shall be construed as to abrogate any required public notice.

(2) The time limit in this section begins upon the governing body or planning commission's receipt of a request from an applicant.

(3) The governing body or planning commission approves the request, then the governing body or planning commission may not impose on the applicant additional requirements related to the request: Provided, however, That if an applicant submits amendments to previously approved plans or petitions, those amendments may be considered a new request.

(4) The governing body or planning commission denies the request, then the governing body or planning commission must provide the applicant a statement in writing of the reasons for the denial.

(5) A governing body or planning commission denies a request for being incomplete, then the governing body or planning commission must provide the applicant a statement in writing of the reasons the request is incomplete. The request is incomplete if the request fails to contain all information required by law or by a previously adopted rule, ordinance, or policy.

§8A-13-3. Extension.

The time limit in §8A-13-2 of this code may be extended. The following applies:

The time limit in §8A-13-2 of this code is extended if a request requires prior approval of a state or federal agency. The time limit is extended to 60 120 days after the required prior approval is granted. The extension may not exceed 60 120 days, unless approved by the applicant.

An applicant may request an extension in writing.

 

NOTE: The purpose of this bill is to expand the deadlines for permitting to ensure the petitioners have adequate time for review and approval by local administrators and eliminate conflicts with other legal notice requirements for the type of approvals required under chapter 8A.

Strike-throughs indicate language that would be stricken from a heading or the present law and underscoring indicates new language that would be added.